Project Schedule

The County of Monmouth, with the cooperating agencies of NJTPA and NJDOT, will provide updates in an effort to keep the community and general public informed of current progress on the County Route 537 West Main Street corridor roadway improvements project.

Project Schedule (Phases)

Local Concept Development (LCD) Phase

2011 – 2014 completed

Local Preliminary Engineering (LPE) Phase

2015 – 2019 completed

Final Design (FD) Phase

2020 – 2026

Construction Phase

2026 – 2028

Final Design Phase – Project Schedule (Major Milestones)

Environmental Permits

Spring 2021

ROW Availability / Easements

Summer 2025

PS&E Plans

Spring 2026

Completion of Final Design Phase

Spring 2026

Final Design Phase  – Anticipated Community Involvement Schedule

Local Officials Meetings No. 1, No. 2, and No. 3

February 2021, June 2023, August 2025

Community Stakeholders Meeting No. 1

September 2021

Public Information Center (PIC) Meeting

February 2026