MONMOUTH COUNTY

County Route 537 (CR 537)

West Main Street Corridor Improvements

Between Sentinel Road and U.S. Route 9 Interchange

Freehold Township

Project Schedule

The County of Monmouth, with the cooperating agencies of NJTPA and NJDOT, will provide updates in an effort to keep the community and general public informed of current progress on the County Route 537 West Main Street corridor roadway improvements project.

Local Concept Development (LCD) Phase2011 – 2014 completed
Local Preliminary Engineering (LPE) Phase2015 – 2019 completed
Final Design (FD) Phase2020 – 2023
Construction Phase2023 – 2025
Environmental PermitsFall 2021
ROW Availability / EasementsSpring 2023
PS&E PlansSpring 2023
Completion of Final Design PhaseSummer 2023
Local Officials Meetings No. 1 and No. 2February 2021, Winter 2022
Community Stakeholders Meetings No. 1 and No. 2September 2021, Spring 2022
Public Information Center (PIC) MeetingSpring 2023

Do you have a comment or suggestion?  Are you a new resident or business owner in the area of the project? Feel free to contact us and use the online comment form for questions or comments or to be added to the contact mailing list.