The County of Monmouth, with the cooperating agencies of NJTPA and NJDOT, has created this page to share information with the community and general public of the current progress on the CR537 West Main Street Corridor Roadway Improvements Project:
Final Design Phase Work Effort (January 2020 – present)
On-Going Community Involvement & Public Outreach
Local Officials Meeting No. 1 – held February 2021
Community Stakeholders Meeting No. 1 – held September 2021
Right-of-Way (ROW) notification letters to affected property owners – mailed February 2022
Mailing of parcel maps and descriptions to affected property owners and scheduling of individual meetings with Monmouth County ROW representatives and appraisers – anticipated Spring to Fall 2022
Local Officials Meeting No. 2 – anticipated Spring 2022
Community Stakeholders Meeting No. 2 – anticipated Fall 2022
Public Information Center Meeting No. 1 – anticipated Spring 2023
On-Going Engineering and Environmental Items
Complete Final Design Plans – anticipated Summer 2023
Project Mapping & Field Survey – completed
Geotechnical Borings – completed
Environmental Permits & Approvals – in process
Right-of-Way (ROW) Negotiations & Acquisitions – in process
Conduct Utility Coordination – in process
Develop Engineering Technical Design Plans – in process